???? 據安迅思3月19日消息稱,3月18日,英國石油巨頭英國石油公司宣布,計劃在2030年之前在蒂賽德產業群建設1吉瓦的藍氫設施。
????這個名為H2Teesside的項目將占英國政府雄心勃勃的目標的20%,即在這個十年結束前實現5GW的低碳氫生產。該設施將使用天然氣以及碳捕獲和存儲來產生藍氫。
????該項目將在2024年做出最終投資決定后分階段建設。此后,到2027年或更早的時候,500兆瓦的裝機容量可能會上線,剩余的裝機容量可能會在2030年上線。
????擬議的H2Teesside工廠的碳捕獲率高達98%。
????英國石油公司沒有說明這項技術是將采用自動熱重整(ATR)還是蒸汽甲烷重整(SMR)。
????ATR是蘇格蘭Acorn項目和大曼徹斯特地區的HyNet項目的首選技術。
????英國石油公司表示,H2Teesside項目生產的氫氣將用于工業區,但隨著時間的推移,也可以分配到居民區。
????與此同時,BP與Venator簽署了一份諒解備忘錄,為其旗艦產品二氧化鈦(TiO2)顏料和性能添加劑供應氫氣。
????此外,與英格蘭北部的天然氣分銷商北部天然氣網絡公司(NGN)簽署了一份諒解備忘錄,以向工業和住宅用戶提供脫碳天然氣供應。
????H2Teesside將與該地區的凈零Teesside(BZT)和Northern Endurance Partnership(NEP)碳捕集利用與封存(CCUS)項目整合,這兩個項目均由BP作為運營商領導。
????在此之前,英國政府于3月17日發布了工業脫碳戰略,該戰略將提供1.71億英鎊資金,以減少包括蒂賽德在內的幾個產業集群的排放。
????朱佳妮 摘譯自 安迅思
????原文如下:
????BP announces 1GW blue hydrogen project
????On 18 March British oil major BP announced plans for a 1GW blue hydrogen facility at Teesside industrial cluster by 2030.
????The project, called H2Teesside, would account for 20% of the UK government’s ambition to have 5GW of low-carbon hydrogen production online by the end of this decade. The facility would use natural gas alongside carbon capture and storage to generate blue hydrogen.
????The project will be built in phases following final investment decision, which is due to be taken in 2024. Thereafter, 500MW of capacity could be online by 2027 or earlier, with the remaining capacity potentially online by 2030.
????Carbon capture rates from the proposed H2Teesside plant are as high as 98%.
????BP doesn’t state whether the technology will be autothermal reforming (ATR) or steam methane reforming (SMR).
????ATR is the technology of choice for both the Acorn project in Scotland and the HyNet project around the greater Manchester region.
????According to BP, the hydrogen from the H2Teesside project will be used within the industrial region, but could also be distributed to residential areas with time.
????In line with this, BP has signed a Memorandum of Understanding (MoU) with Venator to supply hydrogen to its flagship titanium dioxide (TiO2) pigments and performance additives.
????A further MoU was signed with Northern Gas Networks (NGN), the gas distributor for the North of England to provide decarbonised gas supply to industrial and residential customers.
????H2Teesside would be integrated with the region’s Net Zero Teesside (BZT) and Northern Endurance Partnership (NEP) carbon capture use and storage (CCUS) projects, both of which are led by BP as operator.
????This announcement follows the UK Government’s Industrial Decarbonisation Strategy released on 17 March, which will provide £171m in funding to reduce the emissions produced by several industrial clusters, including Teesside.